ST. MARYS — City officials unveiled the preliminary 2014 budget during Monday night’s St. Marys Finance Committee meeting.

The proposed budget, which will not  be finalized until later this year, came in at $47.55 million — up slightly from the $45.70 million that was appropriated for 2013. To date, the city has incurred expenses of $20.6 million. The expenses were $40.24 million in 2010, $40.78 million in 2011 and $41.43 million in 2012.

Some big-ticket capital expenditure items include $400,000 for the demolition of the power plant, $910,000 for the 2014 street program and $200,000 for the construction of a paved walking path around K.C. Geiger Park.

City Engineer Craig Moeller called the street program aggressive for next year. The project includes the reconstruction of portions of Oakview Drive — which Moeller placed at approximately $400,000 to $500,000.

This year’s street program was scaled back because of the High Street bridge project.

Kort Fledderjohann will step down from his position as the boys head basketball coach at New...
Division II District Final Celina 48, St. Marys 29 FINDLAY — The Bulldogs held St....
OHSBCA District 8 All-District Teams Division IV Girls Molly Glick, Arcadia Tori Wyss, Ada...

 

Premium Drupal Themes by Adaptivethemes